 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
Case
studies: Pipeline route planning |
|
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
| |
PIPEMON
Pipeline route planning case studies |
| |
| The
route planning procedure, as developed and tested within
the Project, directly incorporates EO data as part of the
overall information base for constraint mapping, and consists
of 4 main steps:
1. Undertake a coarse land
cover analyses, update as required any available land use
GIS, and incorporate overall constraint features. Undertake
an initial ranking of routing options, in overview, to exclude
difficult terrain and pre-select general route corridors.
This process can usually be conducted using more generalized
land cover / land use information, including lower cost
/ lower resolution EO data.
2. Identify viable route alternatives within
those corridors identified in step 1. Pre-select routing
options and spatially delineate critical corridor / route
segments using constraint mapping of input data and information,
including higher resolution EO data or digital airborne
imagery. Constraint evaluations at this stage may also
incorporate a combination of ground-based features/measures.
The result of step 2 is a set of routing alternatives,
such that each corridor / route segment alternative is
associated with different numbers and different weightings
of constraint features.
3. Select those route alternatives that
are associated with fewer and/or lower weighted constraint
features, and undertake further analyses. Step 3 involves
further combination of EO and other spatial / constraint
data / information using GIS modeling and expert knowledge
tools. At this point, it is important that the analyses
are driven by experts familiar with the routing selection
criteria so that, as the investigation proceeds, there
can be iterative refinements applied as constraint features
are evaluated/re-weighted and any remaining information
content requirements determined. Step 3 is then iteratively
repeated, based upon feedback from experts / consultations,
or the addition of new or updated information, for example,
reassessed/updated engineering costing constraints.
4. Conduct one final round of analyses,
incorporating all final GIS modeling rule-sets, appropriate
spatial information and expert knowledge (as applied at
the completion of step 3), to create final constraint
maps. The final outputs which identify one or a few preferred
routing option(s) then need to be checked and further
considered by pipeline planning experts.
Route planning Test Sites 1 and 2, as
outlined below, illustrate the application of steps 3 +
4, and steps 1 + 2, respectively, as described in the paragraph
above.
Results from the two test
sites demonstrate that hard data, such as land cover and
GIS-based positions of existing pipelines, can be appropriately
assessed and weighted along with manually input “soft
information” – for example, information about
interests expressed by adjacent land owners and local planners
to undertake specific activities if certain conditions are
met.
Test Site 1
For a test site in Northern
Germany, Ikonos imagery and other spatial data incorporated
within a land-use GIS were used to help construct constraint
mapping for a section of a proposed pipeline route (see
figure below). Also contained within the project GIS for
the northern German test site was spatial information about
existing pipeline networks, as well as interpreted patterns
of ground movement over time (derived from PSI analyses)
within the vicinity of the proposed pipeline corridor. |
| |
|
Incorporation
of EO and other data within an analytical GIS system, as
a basis for constraint mapping of proposed pipeline routes. |
| |
The
constraint mapping was undertaken using eCognition©
software (see www.definiens.com);
eCognition is an object oriented image analysis software
which intuitively fuses EO data with thematic data like
ESRI? shapefiles, so that derivative analyses can be performed.
In a first step of the route planning constraint mapping,
image objects are created containing all information of
the EO data and the GIS plus their mutual relations. This
enables the planning expert to later access all information
for every area in the test site.
Selection preferences/priorities
as identified by pipeline planning experts were translated
into sets of rules, which the eCognition software could
then use, in a fuzzy logic way, to classify spatial extents
into 5 constraint classes. |
| |
| Test
Site 2 For
a second test site in Germany, two different levels of detail
were analysed (see figure below).
|
| |
|
|
Detailed
analysis |
Coarse
analysis |
Spatial
representation of GIS output from coarse and detailed analysis
of constraint features associated with a proposed pipeline
route. |
| |
The
coarse level 1 analysis, as shown in the above figure, uses
publicly available data such as Landsat imagery and broad
DEM data to generate a generalized overview over the test
site. In the second step (see figure below), areas of interest
were analysed using more detailed input data, such as aerial
photo-imagery and spatially based land use and ownership
data. |
| |
|
Application
of route planning steps 1 and 2 to create constraint maps. |
| |
| The
following general statements were derived from pipeline
operators who provided feedback, in relation to evaluation
of route planning services:
- The Project’s route planning tool
is a good support for the early phases of coarse planning.
- The consideration of existing pipeline
tracks as planning parameter is essential.
- The consideration of planners’ knowledge
in the automated decision process is essential.
- The approach itself shows a promising development
for automated planning support.
Service Strengths
The following general statements
were derived from pipeline operators who provided feedback:
- The service is especially suitable for
sparsely populated remote areas where only spatial information
is available.
- The service may use EO data and include
non-EO data so that a full coverage of the terrain under
investigation can be achieved.
- The service may produce results in a little
time. Once basic data for an area is given different planning
projects can be realized with less effort.
- Automated processing with low costs for
repeated planning runs with changed parameters are possible.
The service may be carried out during non-working hours.
- The service can be used to update and
enhance existing non-EO data using the object recognition
feature.
- In densely populated areas, a preliminary
coarse planning phase may be obsolete because available
corridors are obvious to the planner. In order to achieve
the desired result in these cases, the service requires
a lot of ancillary data to properly reflect the planning
process.
Service Opportunities
The following general statements
were derived from pipeline operators who provided feedback:
- The Project’s planning service gives
a good opportunity for placing further EO based services
within a service portfolio for the pipeline industry.
- The planning service is scalable and allows
the user to initially use a simple version in a smaller
project, and thereafter introduce enhancements for more
complex data requirements or larger pipeline planning
tasks.
- The Project’s methodology appears
to be very useful in terms of addressing main technical
threats for a route planning activity, but there are at
least two issues that need further consideration:
1. Protection of customer
sensitive data: Proposed future pipeline network
configurations are sensitive strategic data for a pipeline
operator, but also needs to be addressed / considered
in the route selection process for an individual route
/ corridor. Perhaps there are ways to protect this larger
corporate information while making portions protected
but available for constraint mapping and route selection
activities; certain services are already in use for
third party interference information.
2. Reduce production
costs (especially in relation to EO data and services
costs): The general uptake of a planning service
product requires adequate pricing. This requires low
data costs, clearly defined costs associated with population
of the GIS analytical tools, and iterative development
of the constraints mapping components. There are perhaps
several ways of reducing costs, such as service/data
pooling, and these should be considered further.
|
| |
|
 |
 |
 |
 |
Designed and hosted by
NPA Group. Site © NPA Group 2006. Content © ESA
& PIPEMON Partners 2006 |
|
 |
 |
|